HIGH POINT SUBSTATION AND TRANSMISSION LINE - CONDITIONAL USE, SITE PLAN AND PLAT | Ready for PC
Folder Name: HIGH POINT SUBSTATION AND TRANSMISSION LINE - CONDITIONAL USE, SITE PLAN AND PLAT
Folder Status: Ready for PC
Project Create Date: Monday, November 2, 2020
Address:
Case Manager: Claire Dalby 303-739-7266
DA Number: DA-2249-00
Number of Comments: 1
Description: CONDITIONAL USE FOR A SUBSTATION IN A MU-A (MIXED USE-AIRPORT) ZONE DISTRICT AND SITE PLAN FOR A DISTRIBUTION SUBSTATION ON 12.0 ACRES WITH ACCOMPANYING 3.8-MILE LONG 230KV TRANSMISSION LINE AND A PLAT FOR ONE LOT ON 12.0 ACRES