GATEWAY PARK IV EAST TIC 2 - PRELIMINARY PLAT | Need 3rd Subm
Type Phase Title Date Resubmit View
Case Files - 2nd Review Comments Need 3rd Subm2nd Review Comments10/7/2020
Case Files - Applicant Response - 1st Review Comments Need 2nd SubmResponse to Comments9/8/2020
Case Files - Letter of Introduction/JustificationNeed 2nd SubmLetter of Introduction9/8/2020
Case Files - 1st Review Comments Need 2nd Subm1st Review Comments7/22/2020
Case Files - Acceptance Letter1st Referral SentAcceptance Letter7/2/2020
Case Files - Referral Memo1st Referral SentReferral Memo7/2/2020
Case Files - Document OneSubmit ApplicationMineral rights Affidavit6/24/2020
Case Files - CorrespondenceSubmit ApplicationArborist Summary6/24/2020
Site Plans - Traffic Impact ReportSubmit ApplicationTraffic Impact Report6/23/2020
Case Files - Response to Pre-app notesSubmit ApplicationResponse to Pre-App Notes6/23/2020